Zone 7 Board Meeting: Mocho PFAS Equipment, New Pleasanton Wells, and a Sites Reservoir Workshop

Sean Roberts•August 19, 2026•5 min read
Zone 7 Board Meeting: Mocho PFAS Equipment, New Pleasanton Wells, and a Sites Reservoir Workshop

The Zone 7 Board of Directors held its regular meeting on August 19, 2026, with all seven directors present. The board met in closed session from 6:05 p.m. to 6:40 p.m., and President Laurene Green reported there was nothing to report out. The open session began at 7:00 p.m.

Mocho PFAS Treatment Plant: early equipment purchase approved 7-0

Associate Civil Engineer Mariza Sibal presented an amendment to the progressive design-build contract with Garney Pacific, Inc. for the Mocho PFAS Treatment Plant.

The background: the Mocho wellfield and the Mocho Groundwater Demineralization Plant are offline because of PFAS. That is a loss of about 16 million gallons per day, or roughly 40% of Zone 7's groundwater production, along with reduced salt management capability. The project will add PFAS removal, upgrade the demineralization plant, improve electrical switchgear, and replace aging well pumps. The adopted capital budget for the project is $55 million.

The action:

  • An Early Works Package of $4.2 million, including a 10% contingency, to buy long-lead electrical equipment such as switchgear, transformers, motor control centers, and variable frequency drives.
  • The total contract not-to-exceed amount rises from $4.2 million to $8.4 million.
  • Staff said buying the equipment before final design shortens the schedule by about 9 to 12 months. Switchgear alone has a lead time of about 52 weeks.
  • Construction is anticipated to begin in 2027, with the plant targeted for completion by the start of summer 2028.

On funding, staff said about $1.2 million in Department of Water Resources grant funding for the electrical equipment has been secured, and about $25 million may be available through the state's Emerging Contaminant Forgivable Loan Program. General Manager Valerie Pryor said the agency expects to hear about the larger amount by the end of the year.

Directors asked whether progressive design-build raises project costs. Assistant General Manager Chris Hentz said the method reduces risk and the potential for significant change orders and delays, and Pryor said there is no evidence that alternative delivery results in higher costs. Staff also said the agency is working with the City of Pleasanton on an easement agreement for the site.

The board approved the amendment 7-0.

Regional Groundwater Development Project: design contract approved 6-1

Associate Civil Engineer Elliott Levitsky presented a contract for preliminary design and owner's representative services for the Regional Groundwater Development Project, a joint project with the City of Pleasanton.

The project:

  • Two new groundwater wells in Pleasanton, intended to increase production capacity in the Bernal subbasin and replace pumping capacity Pleasanton lost when its three wells were removed from service because of PFAS.
  • About 4,000 feet of transmission pipeline to the Hopyard Chloramination Facility, plus upgrades to that facility.
  • A total estimated cost of about $42.3 million, shared with Pleasanton. Zone 7's share is 64% for the wells and pipeline and 77% for the Hopyard facility upgrades.
  • A target completion date of December 2029.

The contract, with Luhdorff & Scalmanini, Consulting Engineers, is for an amount not to exceed $2.25 million, including a 10% contingency.

The discussion:

  • Director Kathy Narum expressed concern about the December 2029 completion date, noting the importance of having the added production available in a multi-year drought. Staff said the critical-path items identified so far are electrical equipment and the PG&E service application, and that starting the PG&E process early would reduce schedule risk.
  • Pryor said the Pleasanton City Council was expected to consider the cooperating agreement on September 1, or September 15 if necessary, and that Zone 7 would not proceed too far ahead of the city's action.
  • Director Jim Lehrman raised concerns about unresolved financial, legal, and environmental risks and about whether pumping could affect migration of the PFAS plume. He suggested an independent third-party review of the groundwater model before proceeding.
  • Director Alan Burnham acknowledged the uncertainty but questioned whether more study would materially improve the decision. He supported the project and recommended operating the wells conservatively.
  • President Green said the information available was sufficient to support the decision and that the groundwater model would continue to be refined.

The board approved the contract 6-1, with Director Lehrman dissenting.

Sites Reservoir Workshop #2

This was an informational workshop with no action requested. Water Resources Manager Ken Minn presented the project and how it could work for Zone 7.

The project. Sites would be a 1.5 million acre-foot off-stream reservoir northwest of Sacramento that captures excess Sacramento River flows after senior water rights and environmental requirements are met. It is targeted to become operational in 2034. Zone 7 has participated since 2016, and its current participation is 62,340 acre-feet of storage, about 4.5% of the reservoir.

Losses along the way. Minn said Delta carriage-water losses are estimated at about 25% to 35%, and water held in the reservoir is subject to evaporation losses of about 8% to 12% a year. In the presentation's example, about two-thirds of a 1,000 acre-foot dry-year release would ultimately be available for delivery.

Storage versus yield. Staff's estimates of average annual yield:

  • 62,340 acre-feet of storage: about 5,000 acre-feet a year, or about 6,000 with the planned Chain of Lakes Conveyance System.
  • 30,000 acre-feet of storage: about 2,500 acre-feet a year, or about 3,000 with the Chain of Lakes Conveyance System.

Cost. Under current projections, keeping 62,340 acre-feet would mean about $1.11 billion in total debt service, averaging about $27 million a year. A 30,000 acre-foot level would mean about $553 million in total debt service, averaging about $14 million a year. In response to a question, Minn estimated the unit cost could exceed $3,500 per acre-foot.

Staff's view. Minn said that, based on current information, a 30,000 acre-foot participation level appears to provide an appropriate balance of cost, benefit, and risk and is consistent with the Urban Water Management Plan. He said the agency would continue evaluating new information before making a final recommendation.

Board discussion. Director Burnham asked whether reducing Sites participation could create added risk if the Delta Conveyance Project is not built and suggested analyzing alternatives. Pryor said the two projects address different needs: Sites provides new water and storage, while Delta Conveyance is intended to preserve the reliability of the State Water Project. Director Sarah Palmer said reducing participation to about 30,000 acre-feet appeared to make sense operationally and financially. President Green confirmed with staff that Zone 7 could sell its Sites water or its participation interest in the future.

Consent calendar

The board approved consent items 8a through 8i on a 7-0 vote. They included:

  • A three-year contract for flood protection strategic and advisory services, not to exceed $235,000.
  • An on-call flood maintenance engineering contract, not to exceed $520,000 over three years.
  • A $286,000 contract with GEI Consultants to evaluate reclamation plan amendments.
  • Project management support for capital improvement projects, not to exceed $495,000 for fiscal year 2026-27.
  • Two new U.S. Geological Survey stream monitoring stations, at Arroyo de la Laguna at Highway 84 and Altamont Creek at Bluebell Drive in Livermore.
  • Appointments to the board of the Association of California Water Agencies Joint Powers Insurance Authority.

The board also approved the July 15 minutes 7-0. The meeting adjourned at 9:52 p.m.

Source: Zone 7 Water Agency, regular board meeting packet and minutes of August 19, 2026.